Performing Art Center Renovation

Performing Arts Center Renovation

Architect: Dykeman Architects

GC/CM: Faber Construction

Estimated Completion: Summer 2025

 Improvements to the Mukilteo School District Performing Arts Center at Kamiak High School (PAC) include lighting and AV system upgrades along with other theater-related systems and components, interior finish upgrades, upgraded signage,  relocation of the existing sound station from the upper level Control Booth to the main level, reconfiguration of seating to accommodate ADA patron locations, and replacement of finishes within the lobby and auditorium. Improvements to the stage will include new draperies, stage flooring, orchestra pit cover, and orchestra shell.

Project Renderings

Project Updates

A stylized illustration of a building with a blue bar and gray text below.

    • Back of house work continues on the stage, including electrical, A/V and painting.
    • Paint and new flooring in the lobby are complete. 
    • Theater controls platform has been expanded, and new railings have been installed. 
    • HVAC upgrades are underway.  

     

    A large, empty room with a concrete floor, a tall light stand, and a small platform in the back.  A set of concrete steps with handrails leading up to a stage or platform.  A view of a hallway with a new rubber tiled floor, a trash can, and a door leading outside.

    A view of a large, empty stage with scaffolding and equipment, suggesting a theater or performance space under construction.  A ladder leans against a wall with a large amount of electrical wiring and cables.

     

    • Electrical trench demo and new electrical infrastructure installed
    • Demolition of existing theater seating
    • Demolition of existing theater rigging system
    • New flooring installed in lobby
    • New paint in lobby and concessions