Explorer Middle School - Phase 1
Explorer Middle School - Phase 1
Explorer Middle School was built in 1973 with some renovations in 1989 and 2005. The school is located within the City of Everett on 29.5 acres. Permanent square footage is 129,296 and there are 8 portable classrooms. A master plan for an entire school replacement and determining Phase I scope has been completed. In Phase I a new stand-alone building will be constructed including a gymnasium, auxiliary gymnasium, fitness room and associated support spaces. The new building will be approximately 21,400 gross square feet. The football field and track will be replaced with a synthetic turf field and rubberized track. Site work will include walkways, landscaping, and utilities. The district anticipates construction starting in Summer 2024 and completion in Fall 2025.
Project Renderings
Exterior
Lobby
Main Gym
Exterior
Fitness Room
Project Updates

-
- Students, staff and the community were welcomed back to the 25-26 school year with a new gym, aux gym, training room, and track & field.
- Contractor working on punch list as part of closeout for Phase 1.


-
- Asphalt paving on the south and east side of the building is complete.
- Concrete sidewalks and driver are being laid out and will be poured the week of 7/28.
- Building signage is complete.
- The track and field is going through its final clean and will be open to the public in early August.
- Gym floor is complete.
- Casework is finished in the corridor.
-
- Track and field installation are complete. Striping was finished in June.
- Landscape work commenced around the field.
- Mat mover installed in gym.
- Fitness porch has been painted.
- Gym floor onsite acclimatizing before installation.
- Fine grading for ramp to fields is underway.
- Interior finishes are ongoing.
- Ceiling grid is complete.
- Electrical trim-out is ongoing.
- Aux gym floor striping is complete.


-
- Aux gym painting is complete.
- Main gym painting is nearing completion.
- Main gym basketball hoops are installed.
- Fitness room wall protection is in progress.
- Main corridor wall protection is underway.
- Rubber track is being installed.



-
- Exterior finishes and roof detailing are 90% complete.
- Interior painting is 50% complete.
- Interior wall finishes are underway (Paneling, toilet room protection, etc.)
- Ceiling grid in installation is in progress.
- Concrete floor polishing is in progress.
- Exterior glass is complete.




-
- Brick work is complete.
- Glazing is complete.
- Exterior metal panel installation is underway.
- Interior drywall installation is progressing.
- Electrical and mechanical rough-in is nearing completion.
- Interior paint has begun.


-
- Interior framing is nearing completion.
- Mechanical, electrical and plumbing (MEP) rough-in is almost ready for wall cover.
- Masons are on-site setting scaffolding and preparing to lay brick.
- Window storefront installation is in progress on the first floor.
- HVAC duct is nearing completion.
- Field turf installation has begun.


-
- Track and field work is progressing – Rubberized e-layer has been installed at field. Turf will be installed next.
- Storage building at field has been framed.
- Interior framing and MEP rough-in is ongoing.
- Exterior sheathing and roofing is in progress.



-
- A topping out celebration was held on December 4th, where staff and the contractor were able to sign the steel beam. The final beam was placed on a primary structural frame.
- Metal roof decking was completed in December.
- The contractor installed a new water line from the main in the street to the new building.
- Exterior metal stud framing is in progress.
- Field work continues with goal posts recently installed.




-
- We are vertical! Ironworkers on site have the primary structrure framed and the roof joists installed on the gym/aux gym.
- Above ground plumbing work is ongoing.
- Weather has allowed continued work on the field grading and rock layer.
- New field house slab has been prepped.


-
- All underground utility work is complete, and the floor slab has been poured.
- The track and field are now at subgrade elevation. Work is wrapping up for the winter and will restart in the spring.
- Storm storage vault is in place under the center field.
- Curbs and fence posts are 90% complete around the track.


-
- Underground work at the new building pad is nearing completion.
- There have been two concrete pours of approximately 140 CY, each for the footings and foundation walls. Building slab on grade is next, followed by exterior walls.
- The stormwater storage system under the field has been installed and the grading is near completion. Crushed rock will be spread over the footprint of the track and field to prepare for winter until work can resume in the spring.


-
- Trenching and underground work ongoing.
- Field has been stripped and drainage demo’d.
- Underground storm utility excavation is underway.


-
- Contractor has mobilized onsite.
- Site excavation is underway.