Skip to main content
District

Mukilteo Elementary - Phase 1

Mukilteo Elementary - Phase 1

 

 

Architect: Hutteball + Oremus Architecture

GC/CM: Spee West Construction

Estimated Completion: Fall 2025

Mukilteo Elementary School was built in 1982. The school is located within the City of Mukilteo on 9.8 acres. Permanent square footage is 41,727 and there are ten (10) portable classrooms. A master plan for an entire school replacement including the scope of Phase I has been completed. Phase I will relocate ten (10) existing classrooms into a new building.  The new building will be approximately 19,973 square feet.  The project will include site work consisting of a play area, walkways, fire lane improvements, and landscaping.  New utility services will include a storm detention system.  The district anticipates construction starting in Summer 2024 and completion in Fall 2025.

Project Renderings

Project Updates

Timeline

    • Contractor completed excavation of the foundation in September. 
    • Forming of the foundation walls is underway with multiple days scheduled for concrete pours. 
    • Soil backfill of the storm retention is complete.
    • Contractor is prepping site for the upcoming rainy season. 

    A construction site with a concrete pump truck pouring concrete into a foundation. A concrete pump truck pours concrete into a large foundation formwork.

    A construction site with a concrete foundation being built, featuring rebar and wooden supports.

    • The civil contractor removed a large boulder found underground while digging the storm retention vault. 
    • Media filters have been installed (storm vault) and covered over with crushed rock. 
    • Utility work continues onsite.
    • Hard surface area prep is underway in preparation for the start of school in September. 

    Workers install a black drainage system in a large, excavated area. A construction site with a concrete truck, workers, and a blue and red fence in front of houses.

    A paved playground with a basketball hoop, a slide, and a climbing structure. A construction site with a large, open area, surrounded by trees and buildings.

    Two excavators work together to move a large boulder at a construction site.

    • Site preparation and excavation is underway.
    • Electrical contractor is installing temporary utility lines to power construction site. 
    • Dirt work contractor is excavating storm retention on the north side of the site.  

    A backhoe is digging a hole in the ground. A construction site with a backhoe and piles of dirt.

    • Permits issued by City of Mukilteo. 
    • Contractor kicked off construction on June 26.